A supplier might deliver late. A supplier has delivered late. Those sentences differ by a few words, but they describe different management situations. In PMP risk-versus-issue questions, tense is useful evidence.
Do not stop at spotting a keyword, though. Read what is uncertain, what has already happened, and what decision the question asks you to make.
Separate uncertainty from the current condition
A risk concerns uncertainty that could affect objectives. An issue is a current condition or problem requiring attention. Risks can involve potential benefits as well as threats. An issue does not have to be something you previously predicted.
PMI discusses this distinction in its project risk management overview. For practice, the useful habit is to describe the condition in plain language before deciding how to respond.
Try three short examples
- The supplier may miss next month's delivery. The delay is uncertain. Assess the risk, identify an owner, and consider an appropriate response.
- The delivery date passed yesterday and the equipment is absent. The missed delivery is now a current issue. Determine the impact and coordinate action.
- The equipment is absent, and the team may miss a later milestone. A current issue and a future uncertainty coexist.
The third example is where a simple label can become misleading. Calling everything a risk overlooks the current problem. Calling everything an issue overlooks what is still uncertain.
A record is useful, but it does not solve the problem
Risk registers and issue logs help preserve ownership, status, and decisions. Updating a record may be appropriate, but it is not a magic first action in every scenario. If an established response must be activated immediately, or a safety concern requires containment, action and communication cannot wait for a beautifully formatted log entry.
Likewise, if the question says the issue is already recorded, selecting record the issue again may fail to move the work forward. Read the sequence already described.
Use the response that fits the evidence
Suppose a known supplier risk occurs and an approved contingency response is available. Check the trigger, authority, and circumstances, then coordinate the appropriate response. Do not invent a new process just because the original plan is less dramatic.
If no suitable response exists, work with the relevant people to assess options and impacts. Escalate when the decision exceeds your authority or the situation requires it. Track the action to resolution and consider any new risks it creates.
Explain both the label and the action
During review, write two sentences: the current condition is... and the appropriate next action is.... This stops terminology from becoming a substitute for judgment. Knowing that the building is on fire is an accurate classification. It is also an incomplete management response.
Apply the habit to a manageable timed session: register for our free 25-question PMP practice exam. Complete the 30-minute attempt, then review which clues you used and which you missed. The goal is a better next decision, not a prediction based on one short score.
Continue your PMP preparation
Explore what happens when a response affects an approved plan in our PMP change control questions guide.
Explore Zero to PMP, our PMP exam preparation program. The program is being updated with new learning resources, and enrollment is currently closed.
Written by Sabri Calisici, project management instructor since 2008.